| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7021-04 | SUMINISTRO E INSTALACION DE LAMINA TRANSLUCIDA EN AREA ENTRE POLINES INCLUYE SOPORTARIA A BASE DE PTR DE 1 1/2" CAL # 14 PARA SU COLOCACION | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LAM ACANAL R-72 1 | LAMINA ESTRUCTURAL ACANALADA DE 10' R-72 DE CAL # 26 | M2 | 24.000000 | $75.00 | $1,800.00 |
| PIJAS P/BROCA 1 | PIJA P/BROCA AME DE 1/4" x 7/8" | PZA | 76.000000 | $1.50 | $114.00 |
| PTR ESTRUCTURAL 3" 1 | PTR ESTRUCTURAL DE 3" | KG | 300.000000 | $18.00 | $5,400.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 50.000000 | $49.88 | $2,494.00 |
| ACETILENO 1 | ACETILENO | KG | 5.000000 | $130.00 | $650.00 |
| OXIGENO 1 | OXIGENO | M3 | 5.000000 | $39.00 | $195.00 |
| Suma de Material | $10,653.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.800000 | $290.45 | $232.36 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 8.000000 | $233.90 | $1,871.20 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 8.000000 | $181.41 | $1,451.28 |
| Suma de Mano de Obra | $3,554.84 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $14,207.84 |