| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 11 | ESCALERA DE CONCRETO F'c=250 KG/CM2, ARMADA 4 Vs # 3 Y EST # 2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.200000 | $290.45 | $58.09 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 2.000000 | $233.90 | $467.80 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 2.000000 | $181.41 | $362.82 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 2.000000 | $169.01 | $338.02 |
| Suma de Mano de Obra | $1,226.73 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 6.000000 | $159.93 | $959.58 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 30.000000 | $22.84 | $685.20 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 60.000000 | $19.87 | $1,192.20 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.300000 | $1,407.27 | $422.18 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.300000 | $215.24 | $64.57 |
| Suma de Auxiliar | $3,323.73 | ||||
| Costo Directo | $4,550.46 |