| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-24 | CONTRACIMIENTO DE CONCRETO F'c=200 KG/CM2, SECCION 40 x 20 CM, ARMADO CON 6 Vs # 4 Y EST #2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREM 200 1 | CONCRETO PREMEZCLADO F'c=200 KG/CM2 | M3 | 0.080000 | $1,109.86 | $88.79 |
| Suma de Material | $88.79 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006000 | $290.45 | $1.74 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.060000 | $233.90 | $14.03 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.060000 | $181.41 | $10.88 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.060000 | $169.01 | $10.14 |
| Suma de Mano de Obra | $36.80 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 6.000000 | $18.08 | $108.48 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 1.600000 | $19.87 | $31.79 |
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.800000 | $159.93 | $127.94 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.080000 | $215.24 | $17.22 |
| Suma de Auxiliar | $285.44 | ||||
| Costo Directo | $411.03 |