| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4025-05 | TECHUMBRE DE GALVATEJA DE 0.91 x 1.24 M INCLUYE BASE DE ESTRUCTURA DE PTR DE 2", PIJAS AUTOROSCABLES, CUMBRERAS Y REMATES, Y TODO LO NECESARIO PARA SU INSTALACION | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TECH GALVATEJA 1 | TECHUMBRE DE GALVATEJA DE 0.91 x 1.24 M | M2 | 1.000000 | $195.00 | $195.00 |
| PTR ESTRUCTURAL 3" 1 | PTR ESTRUCTURAL DE 3" | KG | 15.000000 | $18.00 | $270.00 |
| PIJA 10 X 1" 1 | PIJAS No. 10 X 1" | PZA | 10.000000 | $1.10 | $11.00 |
| Suma de Material | $476.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.025000 | $290.45 | $7.26 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.250000 | $233.90 | $58.48 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.250000 | $181.41 | $45.35 |
| Suma de Mano de Obra | $111.09 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MOR CEM ARE 1:5 1 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.010000 | $1,187.10 | $11.87 |
| Suma de Auxiliar | $11.87 | ||||
| Costo Directo | $598.96 |