| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4121-01 | DADO DE CONCRETO PREMEZCLADO F'c=200 KG/CM2, SECCION 30 x 40 CM ARMADO CON 12 Vs # 4 Y EST #3 @ 30 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 7.800000 | $16.15 | $125.97 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.160000 | $34.00 | $5.44 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.400000 | $11.28 | $4.51 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 4.000000 | $2.50 | $10.00 |
| CONC PREM 200 1 | CONCRETO PREMEZCLADO F'c=200 KG/CM2 | M3 | 0.120000 | $1,109.86 | $133.18 |
| Suma de Material | $281.01 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006670 | $290.45 | $1.94 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.066670 | $233.90 | $15.59 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.066670 | $181.41 | $12.09 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.066670 | $169.01 | $11.27 |
| Suma de Mano de Obra | $40.89 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 12.000000 | $18.08 | $216.96 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 6.000000 | $22.84 | $137.04 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.120000 | $215.24 | $25.83 |
| Suma de Auxiliar | $379.83 | ||||
| Costo Directo | $701.73 |