| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-10 | CASTILLO DE CONCRETO F'c=200 KG/CM2, SECCION 20 x 20 CM, ARMADO CON 4 Vs # 4 Y EST #2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 3.900000 | $16.15 | $62.99 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.080000 | $34.00 | $2.72 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.050000 | $19.00 | $0.95 |
| DIESEL 1 | DIESEL | LTO | 0.400000 | $11.28 | $4.51 |
| Suma de Material | $71.17 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $290.45 | $1.45 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $233.90 | $11.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $181.41 | $9.07 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.050000 | $169.01 | $8.45 |
| Suma de Mano de Obra | $30.67 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 4.000000 | $18.08 | $72.32 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 1.400000 | $19.87 | $27.82 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.040000 | $1,311.84 | $52.47 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.040000 | $215.24 | $8.61 |
| Suma de Auxiliar | $161.22 | ||||
| Costo Directo | $263.06 |