| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4003-03 | CIMENTACION A BASE DE ZAPATA CORRIDA DE 15 x 60 CM, FABRICACION DE CONCRETO F'c=200 KG/CM2, ARMADO CON 6 Vs # 3 Y EST #2 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 7.000000 | $16.15 | $113.05 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.140000 | $34.00 | $4.76 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.060000 | $19.00 | $1.14 |
| DIESEL 1 | DIESEL | LTO | 0.600000 | $11.28 | $6.77 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 4.000000 | $2.50 | $10.00 |
| Suma de Material | $135.72 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007000 | $290.45 | $2.03 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.070000 | $233.90 | $16.37 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.070000 | $181.41 | $12.70 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.070000 | $169.01 | $11.83 |
| Suma de Mano de Obra | $42.94 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.200000 | $22.84 | $50.25 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 2.100000 | $19.87 | $41.73 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.090000 | $1,311.84 | $118.07 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.090000 | $215.24 | $19.37 |
| Suma de Auxiliar | $229.41 | ||||
| Costo Directo | $408.07 |