| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 4100-18 | APLANADO A BASE DE MORTERO CEMENTO ARENA 1:4 EN MUROS INTERIORES (AREA DE BA脩OS) | M2 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.250000 | $16.15 | $4.04 |
| Suma de Material | $4.04 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007100 | $290.45 | $2.06 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.071400 | $233.90 | $16.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.071400 | $181.41 | $12.95 |
| Suma de Mano de Obra | $31.72 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MOR CEM ARE 1:4 1 | MORTERO CEMENTO ARENA 1:4 | M3 | 0.020000 | $1,314.05 | $26.28 |
| Suma de Auxiliar | $26.28 | ||||
| Costo Directo | $62.03 |