| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4003-09 | CIMENTACION A BASE DE ZAPATA CORRIDA DE 30 x 60 CM, FABRICACION DE CONCRETO F'c=200 KG/CM2, ARMADO CON Vs # 3 @ 18 CM INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 12.000000 | $16.15 | $193.80 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.280000 | $34.00 | $9.52 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.120000 | $19.00 | $2.28 |
| DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 4.000000 | $2.50 | $10.00 |
| Suma de Material | $224.62 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012000 | $290.45 | $3.49 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.120000 | $233.90 | $28.07 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.120000 | $181.41 | $21.77 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.120000 | $169.01 | $20.28 |
| Suma de Mano de Obra | $73.60 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 3.600000 | $22.84 | $82.22 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.180000 | $1,311.84 | $236.13 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.180000 | $215.24 | $38.74 |
| Suma de Auxiliar | $357.10 | ||||
| Costo Directo | $655.33 |