| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1001-23 | FIRME DE CONCRETO PREMEZCLADO F'c=200 KG/CM2 DE 10 CM DE ESPESOR, ARMADO CON MALLA ELECTROSOLDADA 6-6/6-6 SIN ACABADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $24.60 | $27.06 |
| CONC PREM 200 1 | CONCRETO PREMEZCLADO F'c=200 KG/CM2 | M3 | 0.100000 | $1,109.86 | $110.99 |
| Suma de Material | $138.05 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003000 | $290.45 | $0.87 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.030000 | $233.90 | $7.02 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.030000 | $181.41 | $5.44 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.060000 | $169.01 | $10.14 |
| Suma de Mano de Obra | $23.47 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $161.52 |