| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-14 | TRABE DE CONCRETO F'c=250 KG/CM2, SECCION 15 x 35 CM, ARMADO CON 6 Vs # 6 Y EST #3 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006250 | $290.45 | $1.82 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.062500 | $233.90 | $14.62 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.062500 | $181.41 | $11.34 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.062500 | $169.01 | $10.56 |
| Suma de Mano de Obra | $38.34 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.600000 | $159.93 | $95.96 |
| ACERO REF #6 1 | ACERO DE REFUERZO # 6 | KG | 13.500000 | $17.73 | $239.36 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.785000 | $22.84 | $63.61 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.045000 | $1,407.27 | $63.33 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.045000 | $215.24 | $9.69 |
| Suma de Auxiliar | $471.94 | ||||
| Costo Directo | $510.27 |