| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4100-26 | ZARPEO Y AFINE DE MUROS Y CIELOS A PLOMO Y REGLA ASENTADO MORTERO CEMENTO ARENA 1:5 CON ESPESOR PROMEDIO DE 2 CM | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.250000 | $16.15 | $4.04 |
| Suma de Material | $4.04 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.010000 | $290.45 | $2.90 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.100000 | $233.90 | $23.39 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.100000 | $181.41 | $18.14 |
| Suma de Mano de Obra | $44.44 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MOR CEM ARE 1:5 1 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.020000 | $1,187.10 | $23.74 |
| Suma de Auxiliar | $23.74 | ||||
| Costo Directo | $72.22 |