| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PV13-01 | GUARNICION TIPO PECHO PALOMA CON CONCRETO PREMEZCLADO F'c=150 KG/CM2 CON MATERIALES DE LA REGION INCLUYE PASAJUNTAS @ 3.0 M EXCAVACION Y/O RELLENO COMPACTADO, CIMBRA Y DESCIMBRA Y LIMPIEZA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.550000 | $16.15 | $8.88 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.080000 | $34.00 | $2.72 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| CELOTEX 13MM 1 | CELOTEX 13 MM DE ESPESOR | M2 | 0.015000 | $31.00 | $0.47 |
| CONC PREM 150 1 | CONCRETO PREMEZCLADO F'c=150 KG/CM2 | M3 | 0.095000 | $1,039.28 | $98.73 |
| CURACRETO 1 | CURACRETO | LTO | 0.250000 | $18.00 | $4.50 |
| Suma de Material | $122.84 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003000 | $290.45 | $0.87 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.030000 | $233.90 | $7.02 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.030000 | $181.41 | $5.44 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.030000 | $169.01 | $5.07 |
| Suma de Mano de Obra | $18.40 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE | HORA | 0.100000 | $40.78 | $4.08 |
| Suma de Equipo | $4.08 | ||||
| Costo Directo | $145.32 |