| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-69 | SUMINISTRO E INSTALACION DE REJILLA DE ACERO TIPO IRVING DE 1" INCLUYE HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| REJILLA IRVING 2 | REJILLA IRVING PULTRUIDA | M2 | 1.150000 | $2,440.00 | $2,806.00 |
| SOLERA 1"X6"X12 M 1 | SOLERA 1" x 6" x 12.00 M | KG | 0.200000 | $16.00 | $3.20 |
| BISAGRA P/REJ 1 | BISAGRA TUBULAR CON PASADOR DE 3/8" | PZA | 0.500000 | $48.00 | $24.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.400000 | $49.88 | $19.95 |
| OXIGENO 1 | OXIGENO | M3 | 0.250000 | $39.00 | $9.75 |
| ACETILENO 1 | ACETILENO | KG | 0.150000 | $130.00 | $19.50 |
| PINTURA ROJO OXIDO 1 | PINTURA ROJO OXIDO | LTO | 1.000000 | $71.50 | $71.50 |
| Suma de Material | $2,953.90 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.008000 | $290.45 | $2.32 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.080000 | $233.90 | $18.71 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.080000 | $181.41 | $14.51 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.800000 | $169.01 | $135.21 |
| Suma de Mano de Obra | $170.76 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 0.800000 | $111.52 | $89.22 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.800000 | $24.34 | $19.47 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.100000 | $200.73 | $20.07 |
| Suma de Equipo | $128.76 | ||||
| Costo Directo | $3,253.42 |