| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1001-43 | PISO DE CONCRETO DE 10 CM DE ESPESOR F'c= 200 KG/CM2 INCLUYE FRONTERAS, MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $24.60 | $27.06 |
| Suma de Material | $27.06 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.002780 | $290.45 | $0.81 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.027780 | $233.90 | $6.50 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.027780 | $181.41 | $5.04 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.055560 | $169.01 | $9.39 |
| Suma de Mano de Obra | $21.73 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.100000 | $1,311.84 | $131.18 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.100000 | $112.45 | $11.25 |
| Suma de Auxiliar | $142.43 | ||||
| Costo Directo | $191.22 |