| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4002-06 | ZAPATA DE CONCRETO F'c=250 KG/CM2 DE 70 CM DE ANCHO Y 20 CM DE PERALTE ARMADA CON Vs # 4 @ 18 CM EN SENTIDO CORTO Y 15 CM @ 20 CM EN SENTIDO LARGO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007500 | $290.45 | $2.18 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.075000 | $233.90 | $17.54 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.075000 | $181.41 | $13.61 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.075000 | $169.01 | $12.68 |
| Suma de Mano de Obra | $46.00 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.400000 | $159.93 | $63.97 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 8.400000 | $18.08 | $151.87 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.200000 | $1,407.27 | $281.45 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.200000 | $215.24 | $43.05 |
| Suma de Auxiliar | $540.35 | ||||
| Costo Directo | $586.35 |