| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 4032-02 | CONCRETO PREMEZCLADO F'c=150 KG/CM2 INCLUYE IMPERMEABILIZANTE INTEGRAL Y SERVICIO DE BOMBA | M3 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREM 150 C/BOM | CONCRETO PREMEZCLADO F'c=150 KG/CM2 CON BOMBEABLE | M3 | 1.000000 | $1,098.00 | $1,098.00 |
| IMPER INTEG 1 | IMPERMEABILIZANTE INTEGRAL | M3 | 1.000000 | $120.00 | $120.00 |
| Suma de Material | $1,218.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.025000 | $290.45 | $7.26 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.250000 | $233.90 | $58.48 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.250000 | $181.41 | $45.35 |
| Suma de Mano de Obra | $111.09 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $1,329.09 |