| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-19 | VIGA EN ALERO DE LOSA DE CONCRETO ARMADO F'c=250 KG/CM2, SECCION 30 x 40 CM, ARMADA CON 6 Vs # 8 Y EST #3 @ 30 CMS INCLUYE CIMBRA Y DESCIMBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 15.600000 | $16.15 | $251.94 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.320000 | $34.00 | $10.88 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.200000 | $19.00 | $3.80 |
| DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 8.000000 | $2.50 | $20.00 |
| Suma de Material | $295.64 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.014000 | $290.45 | $4.07 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.140000 | $233.90 | $32.75 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.140000 | $181.41 | $25.40 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.140000 | $169.01 | $23.66 |
| Suma de Mano de Obra | $85.87 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #6 1 | ACERO DE REFUERZO # 6 | KG | 36.000000 | $17.73 | $638.28 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.400000 | $22.84 | $54.82 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.240000 | $1,407.27 | $337.74 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.240000 | $215.24 | $51.66 |
| Suma de Auxiliar | $1,082.50 | ||||
| Costo Directo | $1,464.01 |