| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-16 | PEDESTAL DE CONCRETO F'c=250 KG/CM2, SECCION 45 x 45 CM, ARMADO CON 6 Vs # 6 Y EST #4 @ 20 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012500 | $290.45 | $3.63 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.125000 | $233.90 | $29.24 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.125000 | $181.41 | $22.68 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.125000 | $169.01 | $21.13 |
| Suma de Mano de Obra | $76.67 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.900000 | $159.93 | $143.94 |
| ACERO REF #6 1 | ACERO DE REFUERZO # 6 | KG | 13.500000 | $17.73 | $239.36 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 9.970000 | $18.08 | $180.26 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.202500 | $1,407.27 | $284.97 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.202500 | $215.24 | $43.59 |
| Suma de Auxiliar | $892.11 | ||||
| Costo Directo | $968.78 |