| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4120-35 | SUMINISTRO Y COLOCACION DE PUERTA REJA DEACERO DE 5.00 x 2.50 M DE ALTURA INCLUYE TUBERIA REJA VERDE, RIEL ANGULO, RUEDA GUIA, RODILLO DE HULE, PORTA CANDADO, ACCESORIOS, MATERIALES, MANO DE OBRA Y HERRAMIENTA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PUERTA REJA 5.0*2.5 | PUERTA REJA DEACERO DE 5.00 x 2.50 M | PZA | 1.000000 | $15,918.62 | $15,918.62 |
| TUB REJA 2 1/4"*3.1M | TUBERIA REJA VERDE DE 2 1/4" x 3.10 M | PZA | 1.000000 | $527.10 | $527.10 |
| TUBO AC GALV 1 3/8" | TUBO GALVANIZADO DE 1 3/8" | M | 5.000000 | $23.56 | $117.80 |
| RIEL ANG 1/4"*1 1/4" | RIEL ANGULO DE 1/4" x 1 1/4" | ML | 10.500000 | $81.66 | $857.43 |
| RUEDA GUIA EMB 4" 1 | RUEDA GUIA EMBALERADA DE 4" | PZA | 2.000000 | $620.00 | $1,240.00 |
| RODILLO HULE 3" | RODILLO DE HULE LATERAL PARA PORTON 3" | PZA | 2.000000 | $177.84 | $355.68 |
| PORTA CANDADO 60*48 | PORTA CANDADO DE 60 x 48 CM | PZA | 1.000000 | $46.50 | $46.50 |
| Suma de Material | $19,063.13 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.200000 | $290.45 | $58.09 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 2.000000 | $233.90 | $467.80 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 2.000000 | $181.41 | $362.82 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 2.500000 | $169.01 | $422.53 |
| Suma de Mano de Obra | $1,311.24 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.250000 | $200.73 | $50.18 |
| Suma de Equipo | $50.18 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.040000 | $68.74 | $2.75 |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.047500 | $1,170.99 | $55.62 |
| Suma de Auxiliar | $58.37 | ||||
| Costo Directo | $20,482.92 |