| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4080-06 | CIMBRA DE MADERA PARA ACABADO COMUN EN TRABES | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 6.700000 | $16.15 | $108.21 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.100000 | $34.00 | $3.40 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 1.100000 | $2.50 | $2.75 |
| Suma de Material | $121.90 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.010500 | $290.45 | $3.05 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.105040 | $233.90 | $24.57 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.105040 | $181.41 | $19.06 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.052520 | $169.01 | $8.88 |
| Suma de Mano de Obra | $55.55 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.013790 | $200.73 | $2.77 |
| Suma de Equipo | $2.77 | ||||
| Costo Directo | $180.21 |