| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6023-13 | DISTRIBUCION DE CIRCUITO ELECTRICO INCLUYE TUBERIA CONDUIT DE PARED DELGADA DE 1/2", 3/4" Y 1" , CAJA CHALUPA Y CABLE CAL # 12 Y 14, HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO COND 1/2" 1 | TUBO CONDUIT 1/2" GALVANIZADO P/GRUESA | M | 1.100000 | $52.33 | $57.56 |
| TUBO COND 3/4" 1 | TUBO CONDUIT 3/4" GALVANIZADO P/GRUESA | M | 1.100000 | $70.13 | $77.14 |
| TUBO COND 1" 1 | TUBO CONDUIT 1" GALVANIZADO P/GRUESA | M | 1.100000 | $79.20 | $87.12 |
| CAJA CHAL 4" 1 | CAJA CHALUPA 4" | PZA | 0.250000 | $8.80 | $2.20 |
| CABLE # 12 1 | CABLE THWN CAL # 12 | M | 1.100000 | $6.45 | $7.10 |
| CABLE # 14 1 | CABLE THWN CAL # 14 | M | 1.100000 | $4.38 | $4.82 |
| Suma de Material | $235.94 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $290.45 | $1.45 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $233.90 | $11.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $181.41 | $9.07 |
| Suma de Mano de Obra | $22.22 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $258.16 |