| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4001-02 | CIMENTACION A BASE DE CONCRETO CICLOPEO 40% PIEDA BOLA 60% CONCRETO F'c=100 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRA BOLA 1 | PIEDRA BOLA | M3 | 1.400000 | $165.00 | $231.00 |
| Suma de Material | $231.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.040000 | $290.45 | $11.62 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.400000 | $233.90 | $93.56 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.400000 | $181.41 | $72.56 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.200000 | $169.01 | $33.80 |
| Suma de Mano de Obra | $211.54 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MOR CEM ARE 1:5 1 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.132000 | $1,187.10 | $156.70 |
| CONCRETO F-C=100 1 | CONCRETO F'C=100 KG/CM2 | M3 | 0.132000 | $1,070.25 | $141.27 |
| Suma de Auxiliar | $297.97 | ||||
| Costo Directo | $740.51 |