| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7020-01 | SUMINISTRO Y COLOCACION DE ACERO ESTRUCTURAL (VIGAS, I.P.R., C.P.S., ETC.). | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VIGA IR 8"*4" 1 | VIGA IR DE 8" x 4" | KG | 1.100000 | $16.00 | $17.60 |
| ACETILENO 1 | ACETILENO | KG | 0.030000 | $130.00 | $3.90 |
| OXIGENO 1 | OXIGENO | M3 | 0.040000 | $39.00 | $1.56 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.050000 | $49.88 | $2.49 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.007000 | $90.00 | $0.63 |
| Suma de Material | $26.18 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001750 | $290.45 | $0.51 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.017500 | $233.90 | $4.09 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.017500 | $181.41 | $3.17 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.017500 | $169.01 | $2.96 |
| Suma de Mano de Obra | $10.73 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.030000 | $111.52 | $3.35 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.030000 | $24.34 | $0.73 |
| CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.008000 | $283.06 | $2.26 |
| Suma de Equipo | $6.34 | ||||
| Costo Directo | $43.26 |