| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-45 | SUMINISTRO Y COLOCACION DE COLUMNA METALICA (A-36) DE 91.5 CM DE LONGITUD FORMADAS POR: (TIPO I SOBRE PEDESTAL Y MURO ANCHO) INCLUYE HABILITADO Y MONTAJE | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANGULO 3/8"X3"X3" 1 | ANGULO DE 3" x 3" x 3/8" | KG | 434.000000 | $20.00 | $8,680.00 |
| SOLERA 3"*3/8" 1 | SOLERA 3" x 3/8" | KG | 178.000000 | $16.00 | $2,848.00 |
| PLACA DE ACERO 1/2"1 | PLACA DE ACERO DE 1/2" | KG | 363.000000 | $12.50 | $4,537.50 |
| ACETILENO 1 | ACETILENO | KG | 23.310000 | $130.00 | $3,030.30 |
| OXIGENO 1 | OXIGENO | M3 | 31.080000 | $39.00 | $1,212.12 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 38.850000 | $49.88 | $1,937.84 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 5.439000 | $90.00 | $489.51 |
| Suma de Material | $22,735.27 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 1.400000 | $290.45 | $406.63 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 14.000000 | $233.90 | $3,274.60 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 14.000000 | $181.41 | $2,539.74 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 14.000000 | $169.01 | $2,366.14 |
| Suma de Mano de Obra | $8,587.11 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 23.000000 | $111.52 | $2,564.96 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 23.000000 | $24.34 | $559.82 |
| CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 6.000000 | $283.06 | $1,698.36 |
| Suma de Equipo | $4,823.14 | ||||
| Auxiliar | |||||
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 15.000000 | $121.86 | $1,827.90 |
| Suma de Auxiliar | $1,827.90 | ||||
| Costo Directo | $37,973.42 |