| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-98 | SUMINISTRO E INSTALACION DE PTR DE 1 1/2" x 1 1/2" x 3.29 KG/M INCLUYE HABILITADO Y MONTAJE | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PTR 1 1/2"X3.29 KG/M | PTR ESTRUCTURAL DE 1 1/2" x 3.29 KG/M | KG | 1.100000 | $18.00 | $19.80 |
| ACETILENO 1 | ACETILENO | KG | 0.015000 | $130.00 | $1.95 |
| OXIGENO 1 | OXIGENO | M3 | 0.020000 | $39.00 | $0.78 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.025000 | $49.88 | $1.25 |
| Suma de Material | $23.78 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001000 | $290.45 | $0.29 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.010000 | $233.90 | $2.34 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.010000 | $181.41 | $1.81 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.010000 | $169.01 | $1.69 |
| Suma de Mano de Obra | $6.13 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.030000 | $111.52 | $3.35 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.030000 | $24.34 | $0.73 |
| Suma de Equipo | $4.08 | ||||
| Costo Directo | $33.99 |