| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4120-41 | SUMINISTRO Y COLOCACION DE PUERTA PEATONAL DE 1.00 x 2.40 M CON POSTE PARA BISAGRAS Y POSTE PARA PASADOR FABRICADA A BASE DE PTR DE 2" x 2" INCLUYE MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PUERTA CIC 1.0*2.4 1 | PUERTA PEATONAL DE 1.00 x 2.40 M DE ALTURA | PZA | 1.000000 | $1,550.00 | $1,550.00 |
| PTR 2" X 2" X 1/4" 1 | PTR ESTRUCTURAL DE 2" x 2" x 1/4 (ROJO) | KG | 15.000000 | $18.00 | $270.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 6.600000 | $49.88 | $329.21 |
| ACETILENO 1 | ACETILENO | KG | 2.400000 | $130.00 | $312.00 |
| OXIGENO 1 | OXIGENO | M3 | 3.300000 | $39.00 | $128.70 |
| BISAGRA P/REJ 1 | BISAGRA TUBULAR CON PASADOR DE 3/8" | PZA | 3.000000 | $48.00 | $144.00 |
| Suma de Material | $2,733.91 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.075000 | $290.45 | $21.78 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.750000 | $233.90 | $175.43 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.750000 | $181.41 | $136.06 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.500000 | $169.01 | $253.52 |
| Suma de Mano de Obra | $586.78 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.050000 | $200.73 | $10.04 |
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 1.000000 | $111.52 | $111.52 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 1.000000 | $24.34 | $24.34 |
| Suma de Equipo | $145.90 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.040000 | $68.74 | $2.75 |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.047500 | $1,170.99 | $55.62 |
| Suma de Auxiliar | $58.37 | ||||
| Costo Directo | $3,524.96 |