| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP6 | SILLETAS DE CONCRETO DE 2.36 X 1.30 X 0.60 CM, F'C=250 KG/M2, REFORZADA ARMADO CON VARILLA # 4 @ 25 CM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLERA 3"*3/8" 1 | SOLERA 3" x 3/8" | KG | 7.900000 | $16.00 | $126.40 |
| Suma de Material | $126.40 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.050000 | $290.45 | $14.52 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.500000 | $233.90 | $116.95 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.500000 | $181.41 | $90.71 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.500000 | $169.01 | $84.51 |
| Suma de Mano de Obra | $306.68 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 37.500000 | $22.84 | $856.50 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 1.840000 | $1,407.27 | $2,589.38 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 8.968000 | $112.45 | $1,008.45 |
| Suma de Auxiliar | $4,454.33 | ||||
| Costo Directo | $4,887.41 |