| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP8 | SILLETAS DE CONCRETO DE 1.50 X 3.20 X 1.90 CM, F'C=250 KG/M2, REFORZADA ARMADO CON VARILLA # 4 @ 25 CM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SOLERA 3"*3/8" 1 | SOLERA 3" x 3/8" | KG | 62.400000 | $16.00 | $998.40 |
| Suma de Material | $998.40 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.100000 | $290.45 | $29.05 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.000000 | $233.90 | $233.90 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.000000 | $181.41 | $181.41 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $613.37 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 124.800000 | $22.84 | $2,850.43 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 9.120000 | $1,407.27 | $12,834.30 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 15.300000 | $112.45 | $1,720.49 |
| Suma de Auxiliar | $17,405.22 | ||||
| Costo Directo | $19,016.98 |