| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4022-05 | MURO DE MADERA DE PINO A BASE DE 2" x 4" & 60 CM VERTICALMENTE Y DOS HORIZONTALES EN PISO Y CIELO, FORRADO CON TRIPLAY DE 5/8" | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRIPLAY 5/8" 1 | TRIPLAY DE PINO DE 5/8" | M2 | 1.000000 | $190.00 | $190.00 |
| POLIN MADERA 2"X4" 1 | POLIN DE MADERA DE 2" x 4" | PZA | 0.250000 | $165.00 | $41.25 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.500000 | $34.00 | $17.00 |
| Suma de Material | $248.25 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.015000 | $290.45 | $4.36 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.150000 | $233.90 | $35.09 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.150000 | $181.41 | $27.21 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.150000 | $169.01 | $25.35 |
| Suma de Mano de Obra | $92.00 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $340.25 |