| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4080-08 | CIMBRA ACABADO APARENTE EN MUROS CON TRIPLAY DE 16 MM INCLUYE HABILITADO, CIMBRADO Y DESCIMBRADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRIPLAY 16 MM 1 | TRIPLAY DE PINO DE 16 MM DE ESPESOR | M2 | 0.160000 | $112.00 | $17.92 |
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 6.900000 | $16.15 | $111.44 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.170000 | $34.00 | $5.78 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| ACERO DE REF 3/8" 1 | ACERO DE REFUERZO DE 3/8" | KG | 0.200000 | $14.08 | $2.82 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 0.500000 | $2.50 | $1.25 |
| Suma de Material | $146.74 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.013160 | $290.45 | $3.82 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.131580 | $233.90 | $30.78 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.131580 | $181.41 | $23.87 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.065790 | $169.01 | $11.12 |
| Suma de Mano de Obra | $69.59 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.021050 | $200.73 | $4.23 |
| Suma de Equipo | $4.23 | ||||
| Costo Directo | $220.55 |