| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7020-A1-01 | SUMINISTRO E INSTALACION DE ANGULO DE 1 1/4" x 1 1/4" x 1/4" INCLUYE CORTES, SOLDADURA, PRIMARIO Y PINTURA EPOXICA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANGULO 1/4" X 1" 1 | ANGULO DE 1/4" x 1" x 1" | KG | 1.100000 | $20.00 | $22.00 |
| ACETILENO 1 | ACETILENO | KG | 0.046000 | $130.00 | $5.98 |
| OXIGENO 1 | OXIGENO | M3 | 0.049000 | $39.00 | $1.91 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.080000 | $49.88 | $3.99 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.020000 | $90.00 | $1.80 |
| ADITIVO ANTIRUST 1 | ADITIVO PARA FRENAR CORROSION ANTIRUST | LTO | 0.015000 | $80.00 | $1.20 |
| Suma de Material | $36.88 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.001200 | $290.45 | $0.35 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.012000 | $233.90 | $2.81 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.012000 | $181.41 | $2.18 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.012000 | $169.01 | $2.03 |
| Suma de Mano de Obra | $7.36 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.025000 | $111.52 | $2.79 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.025000 | $24.34 | $0.61 |
| EQ SANDBLAST 1 | EQUIPO PARA SANDBAST CON ACCESORIOS | HORA | 0.025000 | $16.28 | $0.41 |
| Suma de Equipo | $3.80 | ||||
| Costo Directo | $48.05 |