| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4023-02 | LOSA DE CONCRETO F'c=250 KG/CM2 DE 20 CM DE ESPESOR ARMADO CON Vs 1/2" @ 10 CM EN AMBOS SENTIDOS Y ANGULO PERIMETRAL DE 6" DE DIAMETRO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANGULO PER 6" 1 | ANGULO PERIMETRAL 6" (3.66 ML) | PZA | 4.000000 | $266.00 | $1,064.00 |
| Suma de Material | $1,064.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.075000 | $290.45 | $21.78 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.750000 | $233.90 | $175.43 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.750000 | $181.41 | $136.06 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.750000 | $169.01 | $126.76 |
| Suma de Mano de Obra | $460.02 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 12.000000 | $159.93 | $1,919.16 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 155.000000 | $18.08 | $2,802.40 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 1.800000 | $1,407.27 | $2,533.09 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 1.800000 | $215.24 | $387.43 |
| Suma de Auxiliar | $7,642.08 | ||||
| Costo Directo | $9,166.10 |