| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 20 | SUMINISTRO HABILITADO Y COLOCACION DE CIMBRA COMUN EN TRABE DE CIMENTACION INCLUYENDOOBRA FALSA Y DECIMBRADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP035 | barrote 1 1/2" x 4" x 8' | PT | 1.500000 | $5.62 | $8.43 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM de 1.22 x 2.44 mts | M2 | 0.166700 | $92.00 | $15.34 |
| CIAMP090 | polin de 3 1/2"x3 1/2" regular | PT | 1.260000 | $9.80 | $12.35 |
| CLAVO | CLAVO | Kg | 0.150000 | $16.00 | $2.40 |
| COMBUSTIBLE 01 | diesel | LT | 0.450000 | $6.10 | $2.75 |
| ALAMBRON | alambron de 1/4" | kg | 1.000000 | $9.50 | $9.50 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 16 | KG | 0.045000 | $10.35 | $0.47 |
| Suma de Material | $51.23 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.096154 | $731.16 | $70.30 |
| Suma de Mano de Obra | $70.30 | ||||
| Costo Directo | $121.53 |