| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 29 | CASTILLO DE 15 X 15 CMS. DE CONC. DE Fc= 250 KG/ CM2 CON4 VAR. DE 3/8 PULG. VAR. Y EST. DE ALAMBRON DE 1/4 PULG.DIAM. @ 20 CMS Y CIMBRADO Y DESCIMBRADO | MT |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO DIF. DIAM. | ACERO REF.VAR.DIAM. | kg | 2.500000 | $8.50 | $21.25 |
| MADERA DE PINO 3A | MADERA DE PINO 3A | PT | 2.250000 | $7.50 | $16.88 |
| ALAMBRON | alambron de 1/4" | kg | 0.945000 | $9.50 | $8.98 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 16 | KG | 0.100000 | $10.35 | $1.04 |
| CLAVO | CLAVO | Kg | 0.150000 | $16.00 | $2.40 |
| COMBUSTIBLE 01 | diesel | LT | 0.500000 | $6.10 | $3.05 |
| Suma de Material | $53.59 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.100000 | $731.16 | $73.12 |
| Suma de Mano de Obra | $73.12 | ||||
| Equipo | |||||
| AMAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 H.P. CONJUNTO CABEZAL DE 14" | HR | 0.029610 | $50.82 | $1.50 |
| Suma de Equipo | $1.50 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.023600 | $1,036.71 | $24.47 |
| Suma de Auxiliar | $24.47 | ||||
| Costo Directo | $152.67 |