| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| REFU02A | * REFUERZO VERTICAL EN MUROS ARMADO CON 1 VARILLA DEL No.5 (5/8") EN AMBOS EXTREMOS AHOGADA CON CONCRETO F`C=100KG/CM2, INCLUYE ANCLAJE A DALA DE REMATE Y CONTRATRABE, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#5 | ACERO DE REFUERZO DE 5/8" #5 | KG | 1.640000 | $6.50 | $10.66 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.100100 | $12.00 | $1.20 |
| Suma de Material | $11.86 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.050000 | $503.14 | $25.16 |
| Suma de Mano de Obra | $25.16 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.027000 | $764.81 | $20.65 |
| Suma de Auxiliar | $20.65 | ||||
| Costo Directo | $57.67 |