| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 676.03 | *CARPETA ASFALTICA DE 5 CMS. ESPESOR COMPACTADA AL 95% MINIMO ,MEZCLA EN CALIENTE Y COLOCADA CON PAVIMENTADORA, INCLUYE MATERIAL, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC. ASFALTICO | M3 | 0.062500 | $950.00 | $59.38 | |
| Suma de Material | $59.38 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.007410 | $1,291.94 | $9.57 |
| Suma de Mano de Obra | $9.57 | ||||
| Equipo | |||||
| PETROLIZADORA 1 | hora | 0.016700 | $150.00 | $2.51 | |
| EXTENDEDORA ASFALTO | hora | 0.016700 | $250.00 | $4.18 | |
| COMPACTADOR VIBRATOR | Hr. | 0.016700 | $300.00 | $5.01 | |
| COMPACTADOR NEUMATIC | hora | 0.016700 | $175.00 | $2.92 | |
| Suma de Equipo | $14.61 | ||||
| Costo Directo | $83.56 |