| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 668.02 | *PISO DE CONCRETO DE 15 CMS DE ESPESOR A BASE DE CONCRETO PREMEZCLADO CON MUDULO DE RUPTURA DE 40, BAJA CONTRACCION, INCLUYE MICROFIBRA DE POLIPROPILENO,DE ACUERDO A NORMA ASTM C 1116 A RAZON DE 900 GRAMOS/M3 DE CONCRETO, APLICACION DE ASHFORD FORMULA PARA ACABADO PULIDO, MANO DE OBRA, MATERIAL, EQUIPO, Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO MR-40 | CONCRETO PROFESIONAL MR = 40 KG/CM2 MODULO DE RUPTURA, ESPECIAL PARA PAVIMENTOS CON RESISTENCIA A LA FLEXION, DE 15 CMS. DE ESPESOR | m3 | 0.157500 | $1,000.00 | $157.50 |
| CONCRETO MR-40 | CONCRETO PROFESIONAL MR = 40 KG/CM2 MODULO DE RUPTURA, ESPECIAL PARA PAVIMENTOS CON RESISTENCIA A LA FLEXION, DE 15 CMS. DE ESPESOR | m3 | 0.157500 | $1,000.00 | $157.50 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.150000 | $85.76 | $12.86 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.150000 | $85.76 | $12.86 |
| MEMBRANA DE PARAF. | MEMBRANA DE PARAFINA BASE AGUA COLOR BLANCO | lit | 0.075000 | $16.96 | $1.27 |
| MEMBRANA DE PARAF. | MEMBRANA DE PARAFINA BASE AGUA COLOR BLANCO | lit | 0.075000 | $16.96 | $1.27 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| POLIETILENOCAL 600 | POLIETILENO EN ROLLO | M2 | 0.012500 | $9.42 | $0.12 |
| POLIETILENOCAL 600 | POLIETILENO EN ROLLO | M2 | 0.012500 | $9.42 | $0.12 |
| AGUA | AGUA | M3 | 0.021000 | $37.70 | $0.79 |
| AGUA | AGUA | M3 | 0.021000 | $37.70 | $0.79 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| Suma de Material | $348.24 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.031250 | $1,291.94 | $40.37 |
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.031250 | $1,291.94 | $40.37 |
| Suma de Mano de Obra | $80.75 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $165.87 | $0.59 |
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $165.87 | $0.59 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.016665 | $120.04 | $2.00 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.016665 | $120.04 | $2.00 |
| Suma de Equipo | $5.19 | ||||
| Costo Directo | $434.17 |