| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 540.1 | *BANQUETA DE CONCRETO ARMADO DE 10 CMS. DE ESPESOR. F'C=200 KG/CM2, CON MALLA 66/10-10, ACABADO ESCOBILLADO.NO INCLUYE JUNTAS Y CALAFATEOS. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.050000 | $37.70 | $1.89 |
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2AM 3/4" REV. 10 cm +- 2.5 cm | M3 | 0.103000 | $900.00 | $92.70 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.000000 | $7.00 | $7.00 |
| MALLA 6-6 10/10 | MALLA ELECTROSOLDADA DE 6/6 10/10 | M2 | 1.050000 | $15.00 | $15.75 |
| Suma de Material | $117.34 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.050000 | $503.14 | $25.16 |
| Suma de Mano de Obra | $25.16 | ||||
| Costo Directo | $142.49 |