| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| REGACOMETIDA | *REGISTRO DE CONCRETO Fc = 200 KG/CM2, DE 1.16X1.16X1.15 M, REFORZADO No.3 @ 20 CM EN AMBOS SENTIDOS, TAPA DE FO.FO. 84A, CONTRAMARCO, INCLUYE MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAPA DE FOFO 84A | TAPA DE FO.FO. 84A | PZA | 1.000000 | $2,638.72 | $2,638.72 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 59.210000 | $6.50 | $384.87 |
| Suma de Material | $3,023.59 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 4.000000 | $503.14 | $2,012.56 |
| Suma de Mano de Obra | $2,012.56 | ||||
| Auxiliar | |||||
| EXCAVA-MAN | EXCAVACION POR MEDIO MANUAL EN CEPAS, EN MATERIAL CLASE A, MEDIDO EN BANCO, INCLUYE:MATERIALES MANO DE OBRA Y HERRAMIENTA | M3. | 2.700000 | $105.17 | $283.96 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.560000 | $819.38 | $458.85 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 1.660000 | $32.87 | $54.56 |
| Suma de Auxiliar | $797.38 | ||||
| Concepto | |||||
| PLAN-5 | *PLANTILLA DE CONCRETO PREMEZCLADO F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 | 2.250000 | $56.75 | $127.69 |
| CIMDA | *CIMBRA EN MUROS, ACABADO APARENTE, INCLUYE: MATERIALES, ACARREOS, CORTES, HABILITADOS, CIMBRADO, DESCIMBRADO, MANO DE OBRA, EQUIPO Y HERRAMIENTA (P.U.O.T.). | M2 | 10.340000 | $131.70 | $1,361.78 |
| RELL-EXC | *RELLENO TENDIDO Y COMPACTADO AL 95% PVSM CON MATERIAL PRODUCTO DE LA EXCAVACION COLOCADO EN CAPAS NO MAYORES DE 20 CMS. DE ESPESOR. | M3 | 1.040000 | $98.64 | $102.59 |
| Suma de Concepto | $1,592.05 | ||||
| Costo Directo | $7,425.57 |