| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CADEN1 | *CADENA DE CERRAMIENTO DE 20 X 20 CMS, CONCRETO HECHO EN OBRA F'C= 150 KG/CM2, ACABADO APARENTE, ARMADO CON 4 VARILLAS #3 Y ESTRIBOS No. 2@20 CMS, INCLUYE: MATERIALES, ACARREOS, TRASLAPES, AMARRES,CIMBRA, COLADO,MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 2.420000 | $6.50 | $15.73 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.130900 | $12.00 | $1.57 |
| Suma de Material | $17.30 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.083330 | $503.14 | $41.93 |
| Suma de Mano de Obra | $41.93 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.042000 | $877.68 | $36.86 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $36.86 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 0.420000 | $123.76 | $51.98 |
| Suma de Concepto | $51.98 | ||||
| Costo Directo | $148.07 |