| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CS-27 | SUMINISTRO Y COLOCACION DE PINTURA ROJO BERBELLON A TUBERIAS DE 64 MM DE DIAMETRO INCLUYE. MATERIALES MISCELANEOS, ALTURAS. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA BERBELLON | PINTURA BERBELLON | LT | 0.055000 | $56.00 | $3.08 |
| BROCHA 2" | BROCHA 2" | PZA | 0.010000 | $25.00 | $0.25 |
| ESTOPA | ESTOPA | KG | 0.160000 | $25.00 | $4.00 |
| THINNER | THINNER | LT | 0.055000 | $14.00 | $0.77 |
| Suma de Material | $8.10 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.040000 | $413.55 | $16.54 |
| Suma de Mano de Obra | $16.54 | ||||
| Costo Directo | $24.64 |