| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| IMPERMEABI.INT | IMPERMEABILIZANTE INTEGRAL | M3 | 0.363000 | $70.00 | $25.41 |
| IMPERMEABI.INT | IMPERMEABILIZANTE INTEGRAL | M3 | 0.363000 | $70.00 | $25.41 |
| TAPA FO.FO. | TAPA DE Fo.Fo. DE 61cMSA DE DIAMETRO PESADA | PZA | 1.000000 | $2,073.28 | $2,073.28 |
| TAPA FO.FO. | TAPA DE Fo.Fo. DE 61cMSA DE DIAMETRO PESADA | PZA | 1.000000 | $2,073.28 | $2,073.28 |
| TABIQUE ROJO RECOC. | Tabique rojo recocido 7x14x28 Cm. | PZA | 115.000000 | $1.00 | $115.00 |
| TABIQUE ROJO RECOC. | Tabique rojo recocido 7x14x28 Cm. | PZA | 115.000000 | $1.00 | $115.00 |
| Suma de Material | | | | $4,427.38 |
| Mano de Obra | | | | |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 2.000000 | $503.14 | $1,006.28 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 2.000000 | $503.14 | $1,006.28 |
| Suma de Mano de Obra | | | | $2,012.56 |
| Auxiliar | | | | |
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.363000 | $877.68 | $318.60 |
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.363000 | $877.68 | $318.60 |
| CONCRETO F-C=100 H/O | Concreto 100 Kg/cm2 agregado de 38 mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.133000 | $695.15 | $92.45 |
| CONCRETO F-C=100 H/O | Concreto 100 Kg/cm2 agregado de 38 mm, cemento normal revenimiento 8 a 10 cm. | m3 | 0.133000 | $695.15 | $92.45 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 3.000000 | $32.87 | $98.61 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 3.000000 | $32.87 | $98.61 |
| MORTERO CEM-ARE 1:3 | Mortero cemento mortero-arena 1:3 | M3 | 0.225000 | $699.36 | $157.36 |
| MORTERO CEM-ARE 1:3 | Mortero cemento mortero-arena 1:3 | M3 | 0.225000 | $699.36 | $157.36 |
| Suma de Auxiliar | | | | $1,334.04 |
| Concepto | | | | |
| RELLENO-06 | *RELLENO Y COMPACTACIÓN AL 90% DE MATERIAL DE PRODUCTO DE EXCAVACION PARA COMPLEMENTAR CEPAS | M3 | 9.000000 | $130.87 | $1,177.83 |
| RELLENO-06 | *RELLENO Y COMPACTACIÓN AL 90% DE MATERIAL DE PRODUCTO DE EXCAVACION PARA COMPLEMENTAR CEPAS | M3 | 9.000000 | $130.87 | $1,177.83 |
| EXT.17. | ACERO DE REFUERZO DE VARIOS DIAMETROS PARA COLUMNAS FC = 4200 KG/CM2 EN COLUMNAS DE CONCRETO INCLUYE : HABILITADO Y ARMADO , MATERIAL, MANO DE OBRA HERRAMIENTAS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION . | ton | 0.040000 | $9,323.13 | $372.93 |
| EXT.17. | ACERO DE REFUERZO DE VARIOS DIAMETROS PARA COLUMNAS FC = 4200 KG/CM2 EN COLUMNAS DE CONCRETO INCLUYE : HABILITADO Y ARMADO , MATERIAL, MANO DE OBRA HERRAMIENTAS Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION . | ton | 0.040000 | $9,323.13 | $372.93 |
| I3907 | *EXCAVACION CON EQUIPO MECANICO EN MATERIAL TIPO 1, INCLUYE: MANO DE OBRA Y EQUIPO. | m3 | 12.000000 | $31.35 | $376.20 |
| I3907 | *EXCAVACION CON EQUIPO MECANICO EN MATERIAL TIPO 1, INCLUYE: MANO DE OBRA Y EQUIPO. | m3 | 12.000000 | $31.35 | $376.20 |
| DRES-0008 * | EXCAVACION A MANO EN MATERIAL TIPO II, EN SECO HASTA 2.00 M., DE PROFUNDIDAD PARA ALOJAR TUBERIA, INCLUYE AFINE DE TALUDES Y ABUNDAMIENTO | m3* | 1.000000 | $33.63 | $33.63 |
| DRES-0008 * | EXCAVACION A MANO EN MATERIAL TIPO II, EN SECO HASTA 2.00 M., DE PROFUNDIDAD PARA ALOJAR TUBERIA, INCLUYE AFINE DE TALUDES Y ABUNDAMIENTO | m3* | 1.000000 | $33.63 | $33.63 |
| Suma de Concepto | | | | $3,921.17 |
| Costo Directo | | | | $11,695.15 |