| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DALA20X50 | *DALA INTERMEDIA DE 20 X 50 CM, CONCRETO HECHO EN OBRA Fc= 250 KG/CM2, ACABADO APARENTE, ARMADA CON 6 No. 4, E No.3 @ 20, INCLUYE MATERIALES, ACARREOS, TRASLAPES, AMARRES, CIMBRA, COLADO, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.440600 | $12.00 | $5.29 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 4.390000 | $6.50 | $28.54 |
| ACE#6 | ACERO DE REFUERZO DE 3/4" #6 f`y = 4200 kg/ml | KG | 6.280000 | $6.50 | $40.82 |
| Suma de Material | $74.64 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.083333 | $503.14 | $41.93 |
| Suma de Mano de Obra | $41.93 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.105000 | $877.68 | $92.16 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Auxiliar | $92.16 | ||||
| Concepto | |||||
| 305 | SUMINISTRO Y HABILITADO DE CIMBRA APARENTE EN TRABES, Y CORNIZAS A BASE DE TRIPLAY DE PINO DE 16MM DE ESPESOR EN ESTRUCTURA (MAXIMO 4 USOS), INCLUYE OBRA FALSA, CHAFLANES, CONSUMIBLES, DESENCOFRANTE Y DESCIMBRA DE LOS ELEMENTOS, TODOS LOS MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO, ACARREOS HORIZONTALES Y VERTICALES, DESPERDICIOS Y TODO AQUELLO NECESARIO PARA LA CORRECTA Y COMPLETA EJECUCION DE ESTE CONCEPTO, INCLUYE ADEMAS LIMPIEZA DE OBRA Y RETIRO DE SOBRANTES FUERA DE LA OBRA. (P.U.O.T.) | M2 | 1.000000 | $123.76 | $123.76 |
| Suma de Concepto | $123.76 | ||||
| Costo Directo | $332.49 |