| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CAST | *CASTILLO DE CONCRETO ARMADO DE 20 X 20 CM, CONCRETO HECHO EN OBRA Fc= 150 KG/CM2, ACABADO APARENTE, ARMADA CON 4 VARILLAS No. 3, E No.2 @ 20, INCLUYE MATERIALES, ACARREOS, TRASLAPES, AMARRES, CIMBRA, COLADO, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $503.14 | $20.13 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $503.14 | $20.13 |
| Suma de Mano de Obra | $40.25 | ||||
| Herramienta | |||||
| ANDAMIAJE | (%)mo | 0.030000 | $0.00 | $0.00 | |
| ANDAMIAJE | (%)mo | 0.030000 | $0.00 | $0.00 | |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.042000 | $764.81 | $32.12 |
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.042000 | $764.81 | $32.12 |
| Suma de Auxiliar | $64.24 | ||||
| Concepto | |||||
| 230.9 | CIMBRA COMUN EN CIMENTACION A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DECIMBRA, ACARREOS, DESMOLDANTE,DESPERDICIOS. | M2 | 0.420000 | $117.70 | $49.43 |
| 230.9 | CIMBRA COMUN EN CIMENTACION A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DECIMBRA, ACARREOS, DESMOLDANTE,DESPERDICIOS. | M2 | 0.420000 | $117.70 | $49.43 |
| 230.10 | ACERO DE REFUERZO FY=4200 KG/CM2 VARIOS DIAMETROS EN CIMENTACION.INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE. | TN | 0.005790 | $10,160.46 | $58.83 |
| 230.10 | ACERO DE REFUERZO FY=4200 KG/CM2 VARIOS DIAMETROS EN CIMENTACION.INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE. | TN | 0.005790 | $10,160.46 | $58.83 |
| Suma de Concepto | $216.53 | ||||
| Costo Directo | $321.02 |