| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP18 | PINTURA EN TUBERIA DE 75 mm. | M.L. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.120000 | $51.40 | $6.17 |
| THINER | THINER | LT | 0.034000 | $12.00 | $0.41 |
| ESTOPA | Kg. | 0.013000 | $16.00 | $0.21 | |
| Suma de Material | $6.78 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.025000 | $745.14 | $18.63 |
| Suma de Mano de Obra | $18.63 | ||||
| Costo Directo | $25.41 |