| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.11.012 | PLANCHA DE CONCRETO ARMADO F'C=250 KG/CM2 DE 0.65 X 3.46 X 0.10 REFORZADO CON VER No. 3 @ 20 CMS EN AMBOS SENTIDOS EN BARRA COMEDOR EMPLEADOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 7.020000 | $7.00 | $49.14 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.035000 | $14.00 | $0.49 |
| Suma de Material | $49.63 | ||||
| Mano de Obra | |||||
| CUAD OC 42 | jor | 0.500000 | $808.17 | $404.09 | |
| Suma de Mano de Obra | $404.09 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.084000 | $851.14 | $71.50 |
| BAS-CIM | CIMBRA DE MADERA DE PINO DE 3a. ACABADO COMUN EN ESTRUCTURA, INCLUYE: MATERIALES, ACARREOS, DESPERDICIOS, HABILITADO, OBRA FALSA, CIMBRADO, DESCIMBRADO Y LIMPIEZA (POR SUPERFICIE DE CONTACTO), P.U.O.T. | M2 | 1.100000 | $102.15 | $112.37 |
| Suma de Auxiliar | $183.86 | ||||
| Costo Directo | $637.58 |