| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HAM57 | PINTURA EN TUBERIA DE 13 mm | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.040000 | $51.40 | $2.06 |
| PINTURA SHERWIN | PINTURA SHERWIN | LT | 0.040000 | $51.40 | $2.06 |
| THINER | THINER | LT | 0.018000 | $12.00 | $0.22 |
| THINER | THINER | LT | 0.018000 | $12.00 | $0.22 |
| ESTOPA | Kg. | 0.015000 | $16.00 | $0.24 | |
| ESTOPA | Kg. | 0.015000 | $16.00 | $0.24 | |
| Suma de Material | $5.02 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.014290 | $745.14 | $10.65 |
| CUADRILLA BAJA TENS | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.014290 | $745.14 | $10.65 |
| Suma de Mano de Obra | $21.30 | ||||
| Costo Directo | $26.32 |