| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| WCOL2 | COLOCACION Y PRUEBAS DE: INODORO IS OLIMPICO BCO P/FLUXOMETRO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| WC OLIMPICO | WC OLIMPICO | PZA | 0.100000 | $2,100.00 | $210.00 |
| PIJAS WC | PIJAS WC | PZA | 2.000000 | $4.30 | $8.60 |
| TAQUETE 3/8 | TAQUETE 3/8 PLASTICO | PZA | 2.000000 | $0.70 | $1.40 |
| JUNTA SELL | JUNTA SELL | PZA | 6.000000 | $7.80 | $46.80 |
| Suma de Material | $266.80 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.333333 | $758.47 | $252.82 |
| Suma de Mano de Obra | $252.82 | ||||
| Costo Directo | $519.62 |