| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 270.11.015 | TARJA DE PISO EN CUARTO DE ASEO DE CONCRETO ARMADO F'C=200 KG/CM2 DE 0.74 X X1.05 X 0.50 MTS EN MEDIDAS EXTERIORES FIRME DE 10 CM CON PENDIENTE DE 5% MUROS DE 14 CM2 DE ESPESOR ARMADO CON VAR No. 3 @ 25 CM EN AMBOS SENTIDOS, CON ARISTA DE ANGULO DE ACERO A-36 DE 1" X 1" X " CON GRAPAS @ 30 CM EN TRATIENDA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 59.820000 | $7.00 | $418.74 |
| ANGULO 1 1/2" X 1/4" | ANGULO 1 1/2" X 1/4" | KG | 80.000000 | $7.07 | $565.60 |
| Suma de Material | $984.34 | ||||
| Auxiliar | |||||
| EXCAVA-MAN | EXCAVACION POR MEDIO MANUAL EN CEPAS, EN MATERIAL CLASE A, MEDIDO EN BANCO, INCLUYE:MATERIALES MANO DE OBRA Y HERRAMIENTA | M3. | 0.505000 | $114.86 | $58.00 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.735700 | $793.01 | $583.42 |
| ACARRE40M | ACARREO HORIZONTAL SIN PENDIENTE. EN CARRETILLA DE 3.5 FT3, A 40.00 M. INCLUYE CARGA Y DESCARGA DEL MATERIAL | M3 | 0.500000 | $35.89 | $17.95 |
| Suma de Auxiliar | $659.37 | ||||
| Concepto | |||||
| PLAN-5 | PLANTILLA DE CONCRETO PREMEZCLADO F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 | 0.777000 | $61.74 | $47.97 |
| CIMDA | Cimbra en dados,contratrabes y trabes de liga en cimentación, acabado común, incluye: materiales, acarreos, cortes, habilitados, cimbrado descimbrado, mano de obra, equipo y herramienta (P.U.O.T.). | M2 | 1.790000 | $118.10 | $211.40 |
| RELL-EXC | RELLENO TENDIDO Y COMPACTADO AL 95% PVSM CON MATERIAL PRODUCTO DE LA EXCAVACION COLOCADO EN CAPAS NO MAYORES DE 20 CMS. DE ESPESOR. | M3 | 1.040000 | $103.73 | $107.88 |
| Suma de Concepto | $367.25 | ||||
| Costo Directo | $2,010.96 |